06/10/06 - Saturday


Chris marvels at the presence of enough sun to create a shadow

Misc Notes:

  • Raining again. Cool, very humid.
  • Chris trnpt deck boards up to MLA, then over to Poocham to get yesterday's laundry(not dry due to w/d prob), fill water jugs(as backup due to repl filters not arriving), then take trash/recycling
  • Cass am + sat chores. Filling 5gal jug took well over 1hr. No phone signal.
  • Loud 'mowing lawn' sound again. Ugh.
  • Lunch when Chris back. During, saw enough hazy sun to make a shadow. No such luck that it stayed though.
  • Site work at MLA in afternoon.
  • Cold, two batched rocks, dinner + tea, treat Chris
  • Got to bed on schedule (wow!), but then awake much longer (wow!)

275.04 Materials Transport/inventory

  • boards unloaded at MLA
  • Moose does the neutral rolldown without engine running.
  • Cass stayed in yurt with windows closed
  • 50 more deck boards loaded and relocated to Vermont
  • time: 90 min


Cass completes her fourth footing hole

213.01 Footings

  • C&C dug more holes
  • drill pump doesn't have enough juice to suck water uphill thru a 1" PEX tube. Perhaps a smaller tube?
  • time: 4 hrs
  • one seems to be above/near curtain drain.
  • another might be right over MLA water and RF pipes.

303.08 Troubleshoot: water coming out of U.Shed corex and/or at least divert

  • reconfigured temp drain corex
  • time: 30 min

303.10 Fix for water at bottom of steps by woodshed

  • dug trench to route water away
  • time: 0.25hr


Chris digs digging