February 2006
Journal

Here's a list of February happenings. Photos at bottom.

02.04.06

  • Solar panel park ave
  • Started panel rack construction
  • time: 90m

02.11.06

  • Solar panel park ave
  • Finished panel rack construction
  • Wired panel & controller
  • time: 2h

(213.25) Clear area and Construct power house shed

  • cleared some more trees, big ones need to come down next (in spring)
  • time: 1h

02.12.06

  • Solar battery charger/panel
  • Covered outside wire with duct tape as an MCS safety measure
  • time: 30m

02/18/06

  • Solar battery charger/panel
  • finished covering outside wire
  • task completed
  • time: 30m

300.31 Outside area safe for Cass/open windows

  • Cleaned up construction trash @ WC put new trash can behind shed
  • time: 1 hr

213.08 Plumbing in Platform

  • Cut pipe for sink drain
  • time: 30m

02.19.06

300.31 Outside area safe for Cass/open windows

  • moved a buncha stuff into shed & woodshed
  • time: 1:45
  • Drainage
  • emergency repairs under WC platform
  • time: 30m

02.24.06

262.06 Plumbing, interior and hookup [Sink drain]

  • hooked up WC sink vent, installed sink drain
  • time: 1 hr

02.25.06

213.10 attach plywood underneath

  • worked on non-plumbing side, from the middle out
  • time: 1 hr

262.06 Plumbing, interior and hookup [Sink drain]

  • connected trap
  • drain didn't seal properly on the underside, so it leaks. fix it.
  • time 30 min

02.26.06

213.10 attach plywood underneath

  • did a few on non-plumbing edge, this half needs only some screws under very front, do when winter is over & reflectix moved.
  • did a few on the drain chase
  • time: 30 m

 