06/05/06 - Monday
Cass' drainage work at Park Ave
Misc Notes
- Looked like rain all day, but fortunately it didn't . Still cold.
- Chris gets ice and brings up bins from xterra, then work on bug stuff, water filtration and then pack to lv
- Cass ill from ice bags
- Phone signal seems to be doing better (finally, after weeks of not)
305.01 Garlic spray
- another dose of heavy-duty garlic gets sprayed around MLA construction zone and Park Ave. Smells like pizza now.
- time: 2 hrs
305.03 Mosquito dunks in standing water areas
- having learned that BT eats black fly larvae we plan to up the number of Mosquito Dunks (aka donuts of BT) in place. Put four more out.
- time: 15 min
300.29 Water filtration
- Flow from filter is slow, as if cartridge is dirty. Seems odd as its only been in place for three months. Investigating how to clean
- time: 30min
213.27 WC Platform: shape ground for drainage/ lay gravel/stone over site
- More gravel under yurt and raked for sloping. is done for now until finished w/corex
- Filled in area between yurt and SIPPEE
- Shovelled a bit into standing water area for better drainage
- Raked debris out from under porch
- Removed 4x4 posts from corex
- Kept digging on trench for corex
- time: 2.25
Gravel under Welcome Center
|