06/04/06 - Sunday
Cassandra says, "YIPPEE - it's a hole!"
Notes
- Still drizzling a bit, another humid and cold day. But, not raining enough to call off sitework
- Lunch in yurt w/bad 80's song singing
- Access to MLA via driveway and Woody Way OK for Cass w/mask
- She is OK for footing tools, and is shown which to do, and procedures for doing. Might not be good idea for lymphatics w/all the leaning over. But footings progress is really important.
- After dinner, lots of good planning
- Decide to skip transport of all Poocham materials for now. Will move flooring to bedroom for protection/storage, and then finish cleanup
275.04 Materials transport/inventory
- time: 2 hr
- prep for bringing materials from house
marked out platform location at turnaround area.
unloaded platform sections from Vermoose. Yuck! The section on bottom of stack was in a puddle in the truck bed
time: 1.5 hr
213.01 Footings
- put up beams on angled section of deck so footings underneath could be marked
- marked some near-surface footings for drilling
- Cassandra learned the footing hole prep method and dug her first hole
- time: 5 hrs
303.00 Erosion control
- time: 30 min
- moved a bunch of logs and rotted stumpss near Utility shed
213.27 WC Platform: shape ground for drainage/ lay gravel/stone over site
- more digging ditch for corex while waiting for fire/boiling water
- time: 0.25hr
Chris hacks yet another 80's tune
|